Monday, September 2, 2024

TOR For Road Safety Audit

 

TERMS OF REFERENCE FOR ROAD SAFETY AUDIT

 

1.0       Objectives of Road Safety Audit

The objective of Road safety auditing is to identify road safety deficiencies at various stages in the development of road projects/networks so that they can be eliminated or mitigated at the most opportune time to reduce costs and minimize disruption to planning, design, construction and ultimately to enhance the safety of the road environment.

 

2.0       Scope of Work

Road Safety Audit shall be carried out in accordance with the Guideline for the Safety    Audit or Roads and Road Projects in Malaysia and Guideline on Road Safety Audit Management prepared by JKR and shall include audits at the following stages of the project:

 

2.1       Stage 1 Audit – Feasibility and Planning

The Stage 1 will be carried out during the planning phase, where a number of alternative proposals are being considered for the project. Audit is to be made of each alternative, the results of which (to the extent relevant) should be included in the evaluation process.

 

            2.2       Stage 2 Audit – Preliminary Design

The Stage 2 will be carried out at the end of the preliminary design phase where the Functional layout has been prepared and land acquisition requirements are being determined.

 

            2.3       Stage 3 Audit – Detailed Design

This Audit must be done at an appropriate stage towards the end (but not at the end) of the detailed design, or as soon as possible to determine the safety implications of the design and when changes can be made at the most opportune time to avoid costly redesign. This may necessitate separate audit checks as various elements of the project reach the desired stage of design.

A compliance audit report shall be prepared after the designer submitted their compliance report. The audit work at this stage includes auditing the suitability and workability of the proposed traffic management that will be carried out during the construction. The Guidelines on the Estimation Procedures for Traffic Management prepared by JKR will be used as a basis for the traffic management procedures.

 

2.4       Stage 4 Audit – At the Construction/Pre-Opening

The audit at this stage will be carried out three (3) times during the construction duration:

2.4.1    RSA Stage 4 (Part 1) or Verification Audit to be carried out after the issuance construction drawings and Traffic Management Plan (TMP).

This Audit is to ensure that the decision of the S.O/P.D with regard to stage 3 Audit are ‘carried through’ or ‘verified’ in the construction drawings issued to the Contractor for construction.

An Audit of the TMP prepared by the Contractor shall also be carried out before construction works commence to ensure safety of the existing traffic by the construction are taken care of.

 

2.4.2    RSA Stage 4 (Part 2) to be carried out when the construction work’s progress is about 50%.

            It shall include the on-site Traffic Control Plan (TCP) implemented by the Contractor based on the approved TMP.

            Any changes on the TCP shall be documented and approved.

 

2.4.3    RSA Stage 4 (Part 3) to be carried out during the pre-opening of the project. Both day and night audit will be required.

            This Audit is carried out prior to its opening to traffic. Conducted immediately after the construction of the entire project works where it is intended to be opened to traffic. Both day and night audit will be required.

 

2.4.4    Additional Audit of Traffic Management at Work Zone.

            The additional audit of the TCP and on-site Work Zones shall also be carried out during the construction phase at the intervals specified in the Guidelines on Road Safety Audit Management as directed by the S.O/P.D. The audit shall be carried out based on the latest Traffic Management Safety Reports (TMSR) prepared by the Traffic Management officer (TMO) from the contractor’s counterpart.

            This includes the observation of the effectiveness of the Traffic Control Plan (TCP) prepared by the contractor / consultant and the devices employed during the day and night.

            Should the S.O/P.D require additional audit, he shall ask the Road Safety Auditor to carry out the Additional audit and the additional fees shall be agreed upon by the S.O/P.D and the Road Safety Auditor.

            2.5       Stage 5 Audit – Operational

Conducted within 3 or 6 months after the completion of the construction of road infrastructure works. It is typically conducted once traffic patterns have normalized or immediately prior to the change-over of ownership or responsibility in regard to the assets or network operations following the completion of the project.

Also known as the post-opening or operational stage. This is usually carried out within the Defects Liability Period (DLP).

The project development shall not proceed into the next stage of audit before resolution of each of the road safety items identified from the previous audit. JKR reserved the right to commence the audit at the appropriate stages in the development of the road projects.

 

3.0       use of Road Safety Audit Check Lists

 

The Road Safety Audit Guidelines issued by JKR detailed ‘Check Lists’ for each of the above stages of Audit. These Check Lists should be used as a guide and ‘reminder’ of the items to be considered and it needs to be recognized that they do not necessary provide a complete list of the issues or points to be checked. It is the auditor’s responsibility to critically examine all aspects of the project whish may have adverse safety implications, considering carefully the need of all road user groups.

 

4.0       Process Flowchart of Road Safety Audit

The process flowchart in Appendix 1,2,3,4,5,6 and 7 shall be used as guide in the management of the road safety audit.

 

5.0       Road Safety Auditors

            5.1       Roles of Auditor

The principal role of the Auditor is to ensure that safety deficiencies/problems/hazard are identified before they are locked into the design

and/or become a safety problem. The Auditor is expected to highlight all the safety deficiencies in a design/existing road.

The Auditor will look into:

a.       Adoption of appropriate standards

b.      Compliance and non-compliance of standards that will have road safety implications.

The Auditor’s primary role is to look into the safety repercussion of compliance to standard or otherwise and highlight the possible consequences wherever possible of major road safety deficiencies. The Auditor is expected to use his/her experience and wisdom in dealing with the design checkers in these overlapped areas.

 

Figure 1 indicates the position of the matrix of communication between the auditor and other parties:


Figure 1 Matrix of Communication Between the Auditor and Other Parties.

 

5.2       Independence of Auditors

The auditors must be independent of project planners, designers and construction companies involved in the project and have no business or other associations with them.

 

 

6.0       Qualification of Road Safety Auditor

A qualified Road Safety Auditor shall be an engineer who has good understanding of the driver/vehicle/road environment interaction and have experiences in road design, road safety analysis and countermeasures. He shall also be an accredited Road Safety Auditor by Board of engineers (BEM).

 

7.0       Reporting of the Road Safety Auditor

Each stage of the Road Safety Audit shall be reported, in writing, generally as set out in the JKR Guidelines and shall be submitted to the Client within 2 weeks of the audit being done or otherwise as agreed in writing.

The report should specifically describe the safety deficiencies, potential or real, which have been identified along with the relevant references to accepted standards, practices, and road safety principles. The points should be illustrated wherever practicable by ‘marking up’ on the plans or other relevant drawings and / orby color photographs of the items concerned. The report may include the auditors’ suggestions for eliminating or otherwise treating the safety problem identified, but this is not an essential requirement.

The report should not be simply a copy of the ‘Check List’ annotated with ‘ticks’ or ‘crosses’ or ‘yes’ / ‘no’ answers, or in any other way submitted as the Safety Audit Report.

A summary of audit of the audited items shall be prepared by the Auditor together with the audit report.

 

8.0       Handling of Road Safety Audit Report

            8.1       Response Report

A Response Report will be prepared by designer before any completion meeting at any stage of audit. This report is based on the Summary of Audit by the Road Safety Auditor. A Response Report is a document that allows the designer to respond the Road Safety Auditor’s comments or recommendations.

 

            8.2       Completion Meeting

Within 2 weeks of receipt of the Road Safet Audit Report in every stage, JKR/Client shall conduct a completion meeting. In this meeting, the findings are presented by the Road Safety Auditor and discussed. Decisions and actions are to be agreed upon and formally documented.

 

            8.3       Compliance Report

A Compliance report will the be prepared by the designer based on the Summary of Audit from Stage 3 Road Safety Audit Report. The Compliance report is a document indicating designer’s declaration that matters agreed upon in the Road Safety Audit Stage 3 completion meeting has been incorporated in the revised detailed design engineering drawings.

           

            8.4       Compliance Audit

Compliance Audit needs to be carried out by the Road Safety Auditor after receiving the Compliance Report from the designer. This audit produces the Compliance Audit Report which confirms all matters agreed upon in the Road Safety Audit Stage 3 completion meeting has been incorporated by the designer in their detailed design engineering drawings.

 

            8.5       Verification Audit

A Verification Audit (Road Safety Audit Stage 4 Part 1) is to be carried out by the Road Safety Auditor to ensure that all decisions during design stage are implemented in the construction drawings. This audit produces the Verification Audit Report which verifies all matters agreed upon in the completion meeting of the previous Audits have been incorporated in the construction drawings.

Wednesday, July 31, 2024

Our Office Addresses

 

 

 

 

   ZAZ CONSULTANT

                 001895093-v

 

ROAD SAFETY AUDITOR

 

MAIN OFFICE

 

P1-4, PODIUM FLOOR,

PLAZA DWITASIK

JALAN SRI PERMAISURI

BANDAR SRI PERMAISURI

56000 KUALA LUMPUR

TELEPHONE       :  +603 - 91740583           

FACSIMILE           :   +603 - 91717506

EMAIL                   :    zazconsultant8@gmail.com

WHATAPPS                   :     +6012-2599328

NORTHERN BRANCH

 

NO. B1, BAZAR MERGONG II

LOT 6, LORONG PERAK 8

ALOR SETAR 05150

KEDAH DARUL AMAN

TELEPHONE       :  +604 – 7311831

FAX : +604 – 7311831

EMAIL  :   zazconsultant7@gmail.com

 

 

SOUTHERN BRANCH

 

No.26, TINGKAT 1, ARKED MARA

JLN RAHMAT, 83000 BATU PAHAT

JOHOR DARUL TAKZIM

TELEPHONE       :  +6012 - 2653391

EMAIL  :   zazconsultant9@gmail.com


RSA Stage 1, 2, 3, 4 Part 1, 4 Part 2, 4 Part 3 and 5